Planning
Map
Highlights
Development
Planning and
Environment Approvals
We intend to seek a Development Approval as a State Significant Development under the Environmental Planning and Assessment Act 1979 (the EP&A Act) for NSW. We are preparing to submit a scoping report to obtain project-specific environmental assessment requirements. An Environmental Impact Statement will then be prepared to address the requirements as part of our development application.
Equis completed its first community drop-in session on the 18th of October 2024 between 10:00 am to 2:00 pm at the Wanganella Hall, NSW. For material presented at the drop-in session, please click the link below.
Wanganella
Community
Drop-In Session
Serviced NSW Households/Yr
490,000
Direct Operational Jobs
19
Direct Construction Jobs
420
2032
2031
2029
approvals
2024-2027
2024 - 2026
Wanganella Wind Farm will produce, store and dispatch power directly into VNI West enhancing the security and reliability of electricity networks in New South Wales and Victoria.
Wanganella Wind Farm
Wanganella,
New South Wales
The proposed Wanganella Wind Farm is located next to the Cobb Highway in Wanganella, New South Wales.
Wanganella Wind Farm intends to connect to New South Wales' electricity network via a switching station connecting to the proposed 500kV Victoria to New South Wales Interconnector West (VNI West).
Wanganella Wind Farm is expected to commence operations by 2032.
About the
project
Serviced NSW Households/Yr
490,000
Direct Operational Jobs
19
Direct Construction Jobs
420
Planning
Map
Highlights
Development
Planning and
Environment Approvals
We intend to seek a Development Approval as a State Significant Development under the Environmental Planning and Assessment Act 1979 (the EP&A Act) for NSW. We are preparing to submit a scoping report to obtain project-specific environmental assessment requirements. An Environmental Impact Statement will then be prepared to address the requirements as part of our development application.
Equis completed its first community drop-in session on the 18th of October 2024 between 10:00 am to 2:00 pm at the Wanganella Hall, NSW. For material presented at the drop-in session, please click the link below.
Wanganella
Community
Drop-In Session
Wanganella Wind Farm
2032
2031
2029
approvals
2024-2027
2024 - 2026
Wanganella Wind Farm will produce, store and dispatch power directly into VNI West enhancing the security and reliability of electricity networks in New South Wales and Victoria.
Wanganella,
New South Wales
The proposed Wanganella Wind Farm is located next to the Cobb Highway in Wanganella, New South Wales.
Wanganella Wind Farm intends to connect to New South Wales' electricity network via a switching station connecting to the proposed 500kV Victoria to New South Wales Interconnector West (VNI West).
Wanganella Wind Farm is expected to commence operations by 2032.